Example of Default Exporting in Blazor Gantt Chart Component
This sample demonstrates the client-side exporting of Gantt, which allows you to export Gantt data to Excel, CSV, and PDF formats. Using the Gantt toolbar buttons, you can export Gantt data to the desired format.
ID | Task Name | Start Date | End Date | Progress | Dependency |
---|
1 | Planning and Permits | 4/2/2025 | 4/11/2025 | 100 | |
2 | Site Evaluation | 4/2/2025 | 4/4/2025 | 100 | |
3 | Obtain Permits | 4/7/2025 | 4/9/2025 | 100 | 2FS |
4 | Finalize Planning | 4/10/2025 | 4/11/2025 | 100 | 3FS |
5 | Site Preparation | 4/14/2025 | 4/30/2025 | 100 | |
6 | Site Clearing | 4/14/2025 | 4/14/2025 | 100 | 4FS |
7 | Grading and Excavation | 4/15/2025 | 4/17/2025 | 100 | 6FS |
8 | Foundation Work | 4/18/2025 | 4/21/2025 | 100 | 7FS |
9 | Foundation and Basement | 4/22/2025 | 4/30/2025 | 100 | |
10 | Pour Foundation | 4/22/2025 | 4/23/2025 | 100 | 8FS |
11 | Cure Foundation | 4/24/2025 | 4/25/2025 | 100 | 10FS |
12 | Basement Walls | 4/28/2025 | 4/30/2025 | 100 | 11FS |
13 | Framing | 5/1/2025 | 5/8/2025 | 100 | |
14 | Frame Floors | 5/1/2025 | 5/2/2025 | 100 | 12FS |
15 | Frame Walls | 5/5/2025 | 5/6/2025 | 100 | 14FS |
16 | Install Trusses | 5/7/2025 | 5/8/2025 | 100 | 15FS |
17 | Roofing | 5/9/2025 | 5/13/2025 | 100 | 16FS |
18 | Mechanical, Electrical, Plumbing | 5/14/2025 | 5/23/2025 | 56 | |
19 | HVAC Installation | 5/14/2025 | 5/16/2025 | 100 | 17FS |
20 | Plumbing Installation | 5/19/2025 | 5/21/2025 | 50 | 19FS |
21 | Electrical Installation | 5/22/2025 | 5/23/2025 | 0 | 20FS |
22 | Interior Finishing | 5/26/2025 | 6/13/2025 | 0 | 21FS |
23 | Insulation and Drywall | 5/26/2025 | 5/30/2025 | 0 | 21FS |
24 | Interior Painting | 6/2/2025 | 6/5/2025 | 0 | 23FS |
25 | Flooring Installation | 6/6/2025 | 6/9/2025 | 0 | 24FS |
26 | Cabinet and Fixture Setup | 6/10/2025 | 6/12/2025 | 0 | 25FS |
27 | Final Fixture Installation | 6/13/2025 | 6/13/2025 | 0 | 26FS |
28 | Exterior Finishing | 6/16/2025 | 6/19/2025 | 0 | 27FS |
29 | Landscaping | 6/20/2025 | 6/25/2025 | 0 | 28FS |
30 | Final Inspection | 6/26/2025 | 6/30/2025 | 0 | 29FS |
31 | Correction of Issues | 7/1/2025 | 7/3/2025 | 0 | 30FS |
32 | Final Walkthrough | 7/4/2025 | 7/7/2025 | 0 | 31FS |
33 | Handover Preparation | 7/8/2025 | 7/10/2025 | 0 | 32FS |
34 | Client Handover | 7/11/2025 | 7/11/2025 | 0 | 33FS |
35 | Warranty Period Begins | 7/14/2025 | 7/15/2025 | 0 | 34FS |
36 | Routine Maintenance Visits | 7/16/2025 | 7/25/2025 | 0 | 35FS |
37 | First Year Warranty Review | 7/28/2025 | 8/1/2025 | 0 | 36FS |
38 | Final Project Documentation | 8/4/2025 | 8/6/2025 | 0 | 37FS |
39 | Celebrate Project Completion | 8/7/2025 | 8/8/2025 | 0 | 38FS |
40 | Begin Next Project Planning | 8/11/2025 | 8/13/2025 | 0 | 39FS |
Mar 25, 25 | Mar 30, 25 | Apr 06, 25 | Apr 13, 25 | Apr 20, 25 | Apr 27, 25 | May 04, 25 | May 11, 25 | May 18, 25 | May 25, 25 | Jun 01, 25 | Jun 08, 25 | Jun 15, 25 | Jun 22, 25 | Jun 29, 25 | Jul 06, 25 | Jul 13, 25 | Jul 20, 25 | Jul 27, 25 | Aug 03, 25 | Aug 10, 25 | Aug 17, 25 | Aug 24, 25 | Aug 31, 25 |
T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S |
In this demo, toolbar actions are defined in OnToolbarClick event to export the Gantt data using the ExcelExport and CsvExport methods and PdfExport methods.
More information about exporting in Gantt can be found in this documentation section.