You can select a cell in the Gantt Chart component by setting the SelectionSettings.Mode property to cell. You can get the selected cell information using the GetSelectedRowCellIndexes method. This method returns the result as an object collection, which has CellIndexes and RowIndex information of the selected cells.

Find the code example below to enable the cell selection in Gantt Chart.

@using Syncfusion.Blazor.Gantt
@using Syncfusion.Blazor.Grids
<SfGantt DataSource="@TaskCollection" Height="450px" Width="700px">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" ParentID="ParentId">
    </GanttTaskFields>
    <GanttSelectionSettings Mode="Syncfusion.Blazor.Grids.SelectionMode.Cell"></GanttSelectionSettings>
</SfGantt>

@code{
    private List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public int? ParentId { get; set; }
    }

    public static List<TaskData> GetTaskCollection()
    {
        List<TaskData> Tasks = new List<TaskData>() 
        {
            new TaskData() { TaskId = 1, TaskName = "Project initiation", StartDate = new DateTime(2022, 04, 05), EndDate = new DateTime(2022, 04, 21), },
            new TaskData() { TaskId = 2, TaskName = "Identify Site location", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentId = 1 },
            new TaskData() { TaskId = 3, TaskName = "Perform soil test", StartDate = new DateTime(2022, 04, 05), Duration = "4", Progress = 40, ParentId = 1 },
            new TaskData() { TaskId = 4, TaskName = "Soil test approval", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentId = 1 },
            new TaskData() { TaskId = 5, TaskName = "Project estimation", StartDate = new DateTime(2022, 04, 06), EndDate = new DateTime(2022, 04, 21), },
            new TaskData() { TaskId = 6, TaskName = "Develop floor plan for estimation", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 30, ParentId = 5 },
            new TaskData() { TaskId = 7, TaskName = "List materials", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 40, ParentId = 5 },
            new TaskData() { TaskId = 8, TaskName = "Estimation approval", StartDate = new DateTime(2022, 04, 06), Duration = "0", Progress = 30, ParentId = 5 }
        };
        return Tasks;
    }
}

Cell Selection in Blazor Gantt Chart

Selecting multiple cells

You can select multiple cells by setting the SelectionSettings.Type property to multiple and the SelectionSettings.Mode property to Cell. Multiple cells can be selected by holding the CTRL key and selecting the cells. The following code example demonstrates how to select multiple cells.

@using Syncfusion.Blazor.Gantt
@using Syncfusion.Blazor.Grids
<SfGantt DataSource="@TaskCollection" Height="450px" Width="700px">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" ParentID="ParentId">
    </GanttTaskFields>
    <GanttSelectionSettings Mode="Syncfusion.Blazor.Grids.SelectionMode.Cell" Type="Syncfusion.Blazor.Grids.SelectionType.Multiple"></GanttSelectionSettings>
</SfGantt>

@code{
    private List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime? EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public int? ParentId { get; set; }
    }

    public static List<TaskData> GetTaskCollection()
    {
        List<TaskData> Tasks = new List<TaskData>() 
        {
            new TaskData() { TaskId = 1, TaskName = "Project initiation", StartDate = new DateTime(2022, 04, 05), EndDate = new DateTime(2022, 04, 21), },
            new TaskData() { TaskId = 2, TaskName = "Identify Site location", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentId = 1 },
            new TaskData() { TaskId = 3, TaskName = "Perform soil test", StartDate = new DateTime(2022, 04, 05), Duration = "4", Progress = 40, ParentId = 1 },
            new TaskData() { TaskId = 4, TaskName = "Soil test approval", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentId = 1 },
            new TaskData() { TaskId = 5, TaskName = "Project estimation", StartDate = new DateTime(2022, 04, 06), EndDate = new DateTime(2022, 04, 21), },
            new TaskData() { TaskId = 6, TaskName = "Develop floor plan for estimation", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 30, ParentId = 5 },
            new TaskData() { TaskId = 7, TaskName = "List materials", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 40, ParentId = 5 },
            new TaskData() { TaskId = 8, TaskName = "Estimation approval", StartDate = new DateTime(2022, 04, 06), Duration = "0", Progress = 30, ParentId = 5 }
        };
        return Tasks;
    }
}

Multiple Cell Selection in Blazor Gantt Chart

Selecting a cell dynamically

You can select a cell dynamically using the SelectCellAsync method. Refer to the following code example for details.

@using Syncfusion.Blazor.Gantt
@using Syncfusion.Blazor.Grids
@using Syncfusion.Blazor.Buttons

<SfButton @onclick="SelectCell">Select Cell</SfButton> 
<SfGantt @ref="Gantt" DataSource="@TaskCollection" Height="450px" Width="700px">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" ParentID="ParentId">
    </GanttTaskFields>
    <GanttSelectionSettings Mode="SelectionMode.Cell"></GanttSelectionSettings>
</SfGantt>

@code{
    public SfGantt<TaskData> Gantt;
    public void SelectCell()
    {
        this.Gantt.SelectCellAsync( new ValueTuple<int, int> (1, 2) );
    }
    private List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime? EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public int? ParentId { get; set; }
    }

    public static List<TaskData> GetTaskCollection()
    {
        List<TaskData> Tasks = new List<TaskData>() 
        {
            new TaskData() { TaskId = 1, TaskName = "Project initiation", StartDate = new DateTime(2022, 04, 05), EndDate = new DateTime(2022, 04, 21), },
            new TaskData() { TaskId = 2, TaskName = "Identify Site location", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentId = 1 },
            new TaskData() { TaskId = 3, TaskName = "Perform soil test", StartDate = new DateTime(2022, 04, 05), Duration = "4", Progress = 40, ParentId = 1 },
            new TaskData() { TaskId = 4, TaskName = "Soil test approval", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentId = 1 },
            new TaskData() { TaskId = 5, TaskName = "Project estimation", StartDate = new DateTime(2022, 04, 06), EndDate = new DateTime(2022, 04, 21), },
            new TaskData() { TaskId = 6, TaskName = "Develop floor plan for estimation", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 30, ParentId = 5 },
            new TaskData() { TaskId = 7, TaskName = "List materials", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 40, ParentId = 5 },
            new TaskData() { TaskId = 8, TaskName = "Estimation approval", StartDate = new DateTime(2022, 04, 06), Duration = "0", Progress = 30, ParentId = 5 }
        };
        return Tasks;
    }
}

Selecting Cells Dynamically in Blazor Gantt Chart

Customize cell selection action

While selecting a cell in Gantt Chart, the CellSelecting and CellSelected events will be triggered. The CellSelecting event will be triggered on initialization of cell selection action, and you can get the current selecting cell information to prevent the selection of a particular cell in a particular row. The CellSelected event will be triggered on completion of cell selection action, and you can get the current selected cell’s information. The following code example demonstrates how to prevent the selection of the cell using the CellSelecting event.

@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="450px" Width="700px">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" ParentID="ParentId">
    </GanttTaskFields>
    <GanttSelectionSettings Mode="Syncfusion.Blazor.Grids.SelectionMode.Cell"></GanttSelectionSettings>
    <GanttEvents CellSelecting="CellSelecting" TValue="TaskData"></GanttEvents>
</SfGantt>

@code{
    public void CellSelecting(Syncfusion.Blazor.Grids.CellSelectingEventArgs<TaskData> args)
    {
        if (args.Data.TaskId == 2)
        {
            args.Cancel = true;
        }
    }
    private List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime? EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public int? ParentId { get; set; }
    }

    public static List<TaskData> GetTaskCollection()
    {
        List<TaskData> Tasks = new List<TaskData>() 
        {
            new TaskData() { TaskId = 1, TaskName = "Project initiation", StartDate = new DateTime(2022, 04, 05), EndDate = new DateTime(2022, 04, 21), },
            new TaskData() { TaskId = 2, TaskName = "Identify Site location", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentId = 1 },
            new TaskData() { TaskId = 3, TaskName = "Perform soil test", StartDate = new DateTime(2022, 04, 05), Duration = "4", Progress = 40, ParentId = 1 },
            new TaskData() { TaskId = 4, TaskName = "Soil test approval", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentId = 1 },
            new TaskData() { TaskId = 5, TaskName = "Project estimation", StartDate = new DateTime(2022, 04, 06), EndDate = new DateTime(2022, 04, 21), },
            new TaskData() { TaskId = 6, TaskName = "Develop floor plan for estimation", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 30, ParentId = 5 },
            new TaskData() { TaskId = 7, TaskName = "List materials", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 40, ParentId = 5 },
            new TaskData() { TaskId = 8, TaskName = "Estimation approval", StartDate = new DateTime(2022, 04, 06), Duration = "0", Progress = 30, ParentId = 5 }
        };
        return Tasks;
    }
}