Taskbar editing in Blazor Gantt Chart Component

28 Jun 20222 minutes to read

Modify the task details through user interaction, such as resizing and dragging the taskbar, by enabling the GanttEditSettings.AllowTaskbarEditing property.

@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="450px" Width="900px">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" ParentID="ParentId">
    </GanttTaskFields>
    <GanttEditSettings AllowEditing="true" AllowTaskbarEditing="true"></GanttEditSettings>
</SfGantt>

@code{
    private List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public int? ParentId { get; set; }
    }

    public static List<TaskData> GetTaskCollection()
    {
        List<TaskData> Tasks = new List<TaskData>() {
            new TaskData() { TaskId = 1, TaskName = "Project initiation", StartDate = new DateTime(2022, 04, 02), EndDate = new DateTime(2022, 04, 21), },
            new TaskData() { TaskId = 2, TaskName = "Identify Site location", StartDate = new DateTime(2022, 04, 02), Duration = "0", Progress = 30, ParentId = 1 },
            new TaskData() { TaskId = 3, TaskName = "Perform soil test", StartDate = new DateTime(2022, 04, 02), Duration = "4", Progress = 40, ParentId = 1 },
            new TaskData() { TaskId = 4, TaskName = "Soil test approval", StartDate = new DateTime(2022, 04, 02), Duration = "0", Progress = 30, ParentId = 1 },
            new TaskData() { TaskId = 5, TaskName = "Project estimation", StartDate = new DateTime(2022, 04, 02), EndDate = new DateTime(2022, 04, 21), },
            new TaskData() { TaskId = 6, TaskName = "Develop floor plan for estimation", StartDate = new DateTime(2022, 04, 04), Duration = "3", Progress = 30, ParentId = 5 },
            new TaskData() { TaskId = 7, TaskName = "List materials", StartDate = new DateTime(2022, 04, 04), Duration = "3", Progress = 40, ParentId = 5 },
            new TaskData() { TaskId = 8, TaskName = "Estimation approval", StartDate = new DateTime(2022, 04, 04), Duration = "0", Progress = 30, ParentId = 5 }
        };
        return Tasks;
    }
}