Time Line in Blazor Gantt Chart component

08 Apr 2021 / 26 minutes to read

In the Gantt Chart component, timeline is used to represent the project duration as individual cells with defined unit and formats.

Timeline View Modes

Gantt Chart contains the following in-built timeline view modes:

  • Hour
  • Week
  • Month
  • Year

Timescale mode in Gantt Chart can be defined by using GanttTimelineSettings.TimelineViewMode property and also we can define timescale mode of top tier and bottom tier by using GanttTopTierSettings.Unit and GanttBottomTierSettings.Unit properties.

Following table explains how top tier and bottom tier unit changes as per GanttTimelineSettings.TimelineViewMode property.

Timeline ViewMode Top tier Unit Bottom tier Unit
Year Year Month
Month Month Week
Week Week Day
Day Day Hour
Hour Hour Minute

Week Timeline Mode

In the Week timeline mode, top tier of the schedule header displays the weeks, where as bottom tier of the header displays the days. Refer the following code example.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="450px" Width="900px">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
          Duration="Duration" Progress="Progress" Child="SubTasks">
</GanttTaskFields>
<GanttTimelineSettings TimelineViewMode="TimelineViewMode.Week"></GanttTimelineSettings>
</SfGantt>

@code{
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public List<TaskData> SubTasks { get; set; }
}

public static List <TaskData> GetTaskCollection() {
List <TaskData> Tasks = new List <TaskData> () {
    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 2,
                TaskName = "Identify site location",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "5",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 3,
                TaskName = "Perform soil test",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "5",
                Progress = 50,
            },
            new TaskData() {
                TaskId = 4,
                TaskName = "Soil test approval",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "5",
                Progress = 50,
            },
        })
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 04, 10),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 6,
                TaskName = "Develop floor plan for estimation",
                StartDate = new DateTime(2019, 04, 10),
                Duration = "5",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 7,
                TaskName = "List materials",
                StartDate = new DateTime(2019, 04, 10),
                Duration = "5",
                Progress = 50
            },

        })
    }
};

return Tasks;
}
}

Alt text

Month Timeline Mode

In the Month timeline mode, top tier of the schedule header displays the months, whereas bottom tier of the schedule header displays its corresponding weeks. Refer the following code example.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="450px" Width="900px">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
           Duration="Duration" Progress="Progress" Child="SubTasks">
</GanttTaskFields>
<GanttTimelineSettings TimelineUnitSize=120 TimelineViewMode="TimelineViewMode.Month"></GanttTimelineSettings>
</SfGantt>

@code{
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public List<TaskData> SubTasks { get; set; }
}

public static List <TaskData> GetTaskCollection() {
List <TaskData> Tasks = new List <TaskData> () {
    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 2,
                TaskName = "Identify site location",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "20",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 3,
                TaskName = "Perform soil test",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "20",
                Progress = 50,
            },
            new TaskData() {
                TaskId = 4,
                TaskName = "Soil test approval",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "20",
                Progress = 50,
            },
        })
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 04, 10),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 6,
                TaskName = "Develop floor plan for estimation",
                StartDate = new DateTime(2019, 04, 10),
                Duration = "20",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 7,
                TaskName = "List materials",
                StartDate = new DateTime(2019, 04, 10),
                Duration = "20",
                Progress = 50
            },

        })
    }
};

return Tasks;
}
}

Alt text

Year Timeline Mode

In the Year timeline mode, top tier of the schedule header displays the years, where as bottom tier of the schedule header displays its corresponding months. Refer the following code example.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="450px" Width="900px">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
            Duration="Duration" Progress="Progress" Child="SubTasks">
</GanttTaskFields>
<GanttTimelineSettings TimelineUnitSize=75 TimelineViewMode="TimelineViewMode.Year">
</GanttTimelineSettings>
</SfGantt>

@code{
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public List<TaskData> SubTasks { get; set; }
}

public static List <TaskData> GetTaskCollection() {
List <TaskData> Tasks = new List <TaskData> () {
    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 2,
                TaskName = "Identify site location",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "50",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 3,
                TaskName = "Perform soil test",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "50",
                Progress = 50,
            },
            new TaskData() {
                TaskId = 4,
                TaskName = "Soil test approval",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "50",
                Progress = 50,
            },
        })
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 05, 02),
        EndDate = new DateTime(2019, 09, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 6,
                TaskName = "Develop floor plan for estimation",
                StartDate = new DateTime(2019, 05, 10),
                Duration = "50",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 7,
                TaskName = "List materials",
                StartDate = new DateTime(2019, 05, 10),
                Duration = "50",
                Progress = 50
            },

        })
    }
};

return Tasks;
}
}

Alt text

Day Timeline Mode

In the Day timeline mode, top tier of the schedule header displays the days, where as the bottom tier of the schedule header displays its corresponding hours. Refer the following code example.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" DurationUnit="DurationUnit.Hour" Height="450px" Width="900px">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
          Duration="Duration" Progress="Progress" Child="SubTasks">
</GanttTaskFields>
<GanttTimelineSettings TimelineViewMode="TimelineViewMode.Day"></GanttTimelineSettings>
</SfGantt>

@code{
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public List<TaskData> SubTasks { get; set; }
}

public static List <TaskData> GetTaskCollection() {
List <TaskData> Tasks = new List <TaskData> () {
    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 2,
                TaskName = "Identify site location",
                StartDate = new DateTime(2019, 04, 02, 09, 0, 0),
                Duration = "5",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 3,
                TaskName = "Perform soil test",
                StartDate = new DateTime(2019, 04, 02, 09, 0, 0),
                Duration = "5",
                Progress = 50,
            },
            new TaskData() {
                TaskId = 4,
                TaskName = "Soil test approval",
                StartDate = new DateTime(2019, 04, 02, 09, 0, 0),
                Duration = "5",
                Progress = 50,
            },
        })
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 6,
                TaskName = "Develop floor plan for estimation",
                StartDate = new DateTime(2019, 04, 02, 11, 0, 0),
                Duration = "5",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 7,
                TaskName = "List materials",
                StartDate = new DateTime(2019, 04, 02, 11, 0, 0),
                Duration = "5",
                Progress = 50
            },

        })
    }
};

return Tasks;
}
}

Alt text

Hour Timeline Mode

An Hour timeline mode tracks the tasks in minutes scale. In this mode, the top tier of the schedule header displays hour scale and the bottom tier of the header displays its corresponding minutes.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" DurationUnit="DurationUnit.Minute" Height="450px" Width="900px">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
           Duration="Duration" Progress="Progress" Child="SubTasks">
</GanttTaskFields>
<GanttTimelineSettings TimelineViewMode="TimelineViewMode.Hour"></GanttTimelineSettings>
</SfGantt>

@code{
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public List<TaskData> SubTasks { get; set; }
}

public static List <TaskData> GetTaskCollection() {
List <TaskData> Tasks = new List <TaskData> () {
    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 2,
                TaskName = "Identify site location",
                StartDate = new DateTime(2019, 04, 02, 8, 4, 0),
                Duration = "5",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 3,
                TaskName = "Perform soil test",
                StartDate = new DateTime(2019, 04, 02, 8, 4, 0),
                Duration = "5",
                Progress = 50,
            },
            new TaskData() {
                TaskId = 4,
                TaskName = "Soil test approval",
                StartDate = new DateTime(2019, 04, 02, 8, 4, 0),
                Duration = "5",
                Progress = 50,
            },
        })
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 6,
                TaskName = "Develop floor plan for estimation",
                StartDate = new DateTime(2019, 04, 02, 8, 10, 0),
                Duration = "5",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 7,
                TaskName = "List materials",
                StartDate = new DateTime(2019, 04, 02, 8, 10, 0),
                Duration = "5",
                Progress = 50,
            },

        })
    }
};

return Tasks;
}
}

Alt text

Top Tier and Bottom Tier

Gantt Chart component contains two tier layout in timeline, we can customize the top tier and bottom tier using GanttTopTierSettings and GanttBottomTierSettings properties. Timeline tier’s unit can be defined by using Unit property and Format property was used to define date format of timeline cell and Count property was used to define how many unit will be combined as single cell.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="450px" Width="700px">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
           Duration="Duration" Progress="Progress" Child="SubTasks">
</GanttTaskFields>
<GanttTimelineSettings>
    <GanttTopTierSettings Unit="TimelineViewMode.Month" Format="MMM"></GanttTopTierSettings>
    <GanttBottomTierSettings Unit="TimelineViewMode.Day"></GanttBottomTierSettings>
</GanttTimelineSettings>
</SfGantt>

@code{
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public List<TaskData> SubTasks { get; set; }
}

public static List <TaskData> GetTaskCollection() {
List <TaskData> Tasks = new List <TaskData> () {
    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 2,
                TaskName = "Identify Site location",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "0",
                Progress = 30,
            },
            new TaskData() {
                TaskId = 3,
                TaskName = "Perform soil test",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "4",
                Progress = 40,
            },
            new TaskData() {
                TaskId = 4,
                TaskName = "Soil test approval",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "0",
                Progress = 30,
            },
        })
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 6,
                TaskName = "Develop floor plan for estimation",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "3",
                Progress = 30,
            },
            new TaskData() {
                TaskId = 7,
                TaskName = "List materials",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "3",
                Progress = 40,
            },
            new TaskData() {
                TaskId = 8,
                TaskName = "Estimation approval",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "0",
                Progress = 30,
            },
        })
    }
};

return Tasks;
}
}

Alt text

Combining Timeline Cells

In Gantt Chart, timeline cells in top tier and bottom tier can be combined with number of timeline units, this can be acheived by using GanttTopTierSettings.Count and GanttBottomTierSettings.Count properties. Please refer the below sample.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="450px" Width="700px">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
        Duration="Duration" Progress="Progress" Child="SubTasks">
</GanttTaskFields>
<GanttTimelineSettings TimelineUnitSize="200">
    <GanttTopTierSettings Unit="TimelineViewMode.Year"></GanttTopTierSettings>
    <GanttBottomTierSettings Unit="TimelineViewMode.Month" Format="MMM" Count="6"></GanttBottomTierSettings>
</GanttTimelineSettings>
</SfGantt>

@code{
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public List<TaskData> SubTasks { get; set; }
}

public static List <TaskData> GetTaskCollection() {
List <TaskData> Tasks = new List <TaskData> () {
    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 08, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 2,
                TaskName = "Identify site location",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "150",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 3,
                TaskName = "Perform soil test",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "150",
                Progress = 50,
            },
            new TaskData() {
                TaskId = 4,
                TaskName = "Soil test approval",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "150",
                Progress = 50,
            },
        })
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 05, 02),
        EndDate = new DateTime(2019, 09, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 6,
                TaskName = "Develop floor plan for estimation",
                StartDate = new DateTime(2019, 05, 02),
                Duration = "150",
                Progress = 70,
            },
            new TaskData() {
                TaskId = 7,
                TaskName = "List materials",
                StartDate = new DateTime(2019, 05, 02),
                Duration = "150",
                Progress = 50,
            },
        })
    }
};

return Tasks;
}
}

Alt text

Customize Header Timeline Cells

In the Gantt Chart component, you can format the value of top and bottom timeline cells using the standard date format string or the custom formatter method. This can be done using the GanttTopTierSettings.Format, GanttTopTierSettings.FormatterTemplate, GanttBottomTierSettings.Format and GanttBottomTierSettings.FormatterTemplate properties. The following example shows how to use the formatter method for timeline cells.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="450px" Width="700px" ProjectStartDate="@ProjectStart" ProjectEndDate="@ProjectEnd">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" ParentID="ParentId">
</GanttTaskFields>
<GanttTimelineSettings TimelineUnitSize=50>
    <GanttTopTierSettings Unit="TimelineViewMode.Month" Count="3">
       <FormatterTemplate >
           @{
               @if(context.Tier=="top"){
                   @this.Formatter((context.Date))
               }
           }
       </FormatterTemplate>
    </GanttTopTierSettings>
    <GanttBottomTierSettings Unit="TimelineViewMode.Month" Format="MMM"></GanttBottomTierSettings>
</GanttTimelineSettings>
</SfGantt>

@code{
public DateTime ProjectStart = new DateTime(2019, 01, 10);
public DateTime ProjectEnd = new DateTime(2019, 12, 10);
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public int? ParentId { get; set; }
}
public string Formatter(DateTime? date) {
    DateTime dateTime=(DateTime)(date);
    var month = dateTime.Month;
    if (month >= 0 && month <= 2) {
        return "Q1";
    } else if (month >= 3 && month <= 5) {
        return "Q2";
    } else if (month >= 6 && month <= 8) {
        return "Q3";
    } else {
        return "Q4";
    }
}
public static List <TaskData> GetTaskCollection() {
List <TaskData> Tasks = new List <TaskData> () {

    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 06, 21)
    },
    new TaskData() {
        TaskId = 2,
        TaskName = "Identify Site location",
        StartDate = new DateTime(2019, 04, 02),
        Duration = "20",
        Progress = 30,
        ParentId = 1
    },
    new TaskData() {
        TaskId = 3,
        TaskName = "Perform soil test",
        StartDate = new DateTime(2019, 04, 20),
        Duration = "24",
        Progress = 40,
        ParentId = 1
    },
    new TaskData() {
        TaskId = 4,
        TaskName = "Soil test approval",
        StartDate = new DateTime(2019, 05, 02),
        Duration = "25",
        Progress = 30,
        ParentId = 1
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 06, 02),
        EndDate = new DateTime(2019, 09, 21)
    },
    new TaskData() {
        TaskId = 6,
        TaskName = "Develop floor plan for estimation",
        StartDate = new DateTime(2019, 06, 04),
        Duration = "33",
        Progress = 30,
        ParentId = 5
    },
    new TaskData() {
        TaskId = 7,
        TaskName = "List materials",
        StartDate = new DateTime(2019, 07, 04),
        Duration = "23",
        Progress = 40,
        ParentId = 5
    },
    new TaskData() {
        TaskId = 8,
        TaskName = "Estimation approval",
        StartDate = new DateTime(2019, 08, 04),
        Duration = "20",
        Progress = 30,
        ParentId = 5
    }
};
return Tasks;
}
}

Timeline Cell Width

In the Gantt Chart component, you can define the width value of timeline cell using the GanttTimelineSettings.TimelineUnitSize property. This value will be set to the bottom timeline cell, and the width value of top timeline cell will be calculated automatically based on bottom tier cell width using the GanttTopTierSettings.Unit and GanttTimelineSettings.TimelineUnitSize properties. Refer the following example.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="450px" Width="1000px">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
          Duration="Duration" Progress="Progress" Child="SubTasks">
</GanttTaskFields>
<GanttTimelineSettings TimelineUnitSize=150></GanttTimelineSettings>
</SfGantt>

@code{
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public List<TaskData> SubTasks { get; set; }
}

public static List <TaskData> GetTaskCollection() {
List <TaskData> Tasks = new List <TaskData> () {
    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 2,
                TaskName = "Identify Site location",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "0",
                Progress = 30,
            },
            new TaskData() {
                TaskId = 3,
                TaskName = "Perform soil test",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "4",
                Progress = 40,
            },
            new TaskData() {
                TaskId = 4,
                TaskName = "Soil test approval",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "0",
                Progress = 30,
            },
        })
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 6,
                TaskName = "Develop floor plan for estimation",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "3",
                Progress = 30,
            },
            new TaskData() {
                TaskId = 7,
                TaskName = "List materials",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "3",
                Progress = 40,
            },
            new TaskData() {
                TaskId = 8,
                TaskName = "Estimation approval",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "0",
                Progress = 30
            }
        })
    }
};

return Tasks;
}
}

Alt text

Week Start Day Customization

In the Gantt Chart component, you can customize the week start day using the GanttTimelineSettings.WeekStartDay property. By default,the GanttTimelineSettings.WeekStartDay is set to 0, which specifies the Sunday as a start day of the week. But, you can customize the week start day by using the following code example.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="450px" Width="1000px">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
          Duration="Duration" Progress="Progress" Child="SubTasks">
</GanttTaskFields>
<GanttTimelineSettings WeekStartDay=3></GanttTimelineSettings>
</SfGantt>

@code{
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public List<TaskData> SubTasks { get; set; }
}

public static List <TaskData> GetTaskCollection() {
List <TaskData> Tasks = new List <TaskData> () {
    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 2,
                TaskName = "Identify Site location",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "0",
                Progress = 30,
            },
            new TaskData() {
                TaskId = 3,
                TaskName = "Perform soil test",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "4",
                Progress = 40,
            },
            new TaskData() {
                TaskId = 4,
                TaskName = "Soil test approval",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "0",
                Progress = 30,
            },
        })
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 6,
                TaskName = "Develop floor plan for estimation",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "3",
                Progress = 30,
            },
            new TaskData() {
                TaskId = 7,
                TaskName = "List materials",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "3",
                Progress = 40,
            },
            new TaskData() {
                TaskId = 8,
                TaskName = "Estimation approval",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "0",
                Progress = 30
            }
        })
    }
};

return Tasks;
}
}

Alt text

Customize Automatic Timescale Update action

In the Gantt Chart component, the schedule timeline will be automatically updated when the tasks date values are updated beyond the project start date and end date ranges. This can be enabled or disabled using the GanttTimelineSettings.UpdateTimescaleView property.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="450px" Width="700px">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
         Duration="Duration" Progress="Progress" Child="SubTasks">
</GanttTaskFields>
<GanttEditSettings AllowEditing="true" AllowTaskbarEditing="true"></GanttEditSettings>
<GanttTimelineSettings UpdateTimescaleView="false"></GanttTimelineSettings>
</SfGantt>

@code{
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public List<TaskData> SubTasks { get; set; }
}

public static List<TaskData> GetTaskCollection()
{
    List<TaskData> Tasks = new List<TaskData>() {
    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 2,
                TaskName = "Identify Site location",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "0",
                Progress = 30,
            },
            new TaskData() {
                TaskId = 3,
                TaskName = "Perform soil test",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "4",
                Progress = 40,
            },
            new TaskData() {
                TaskId = 4,
                TaskName = "Soil test approval",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "0",
                Progress = 30,
            },
        })
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 6,
                TaskName = "Develop floor plan for estimation",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "3",
                Progress = 30,
            },
            new TaskData() {
                TaskId = 7,
                TaskName = "List materials",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "3",
                Progress = 40,
            },
            new TaskData() {
                TaskId = 8,
                TaskName = "Estimation approval",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "0",
                Progress = 30
            }
        })
    }
};

    return Tasks;
}
}

Zooming

Gantt Chart have 25 predefined zooming timespan levels from year timespan to hour timespan. This support enables you to view the tasks in a project clearly from minute to decade timespan. To enable the zooming features, define the ZoomIn, ZoomOut, and ZoomToFit items to toolbar items collections. The following zooming options are available to view the project:

Zoom in

This support is used to increase the timeline width and timeline unit from years to minutes timespan. When the ZoomIn icon was clicked, the timeline cell width is increased when the cell size exceeds the specified range and the timeline unit is changed based on the current zoom levels.

Zoom out

This support is used to increase the timeline width and timeline unit from minutes to years timespan. When the ZoomOut icon was clicked, the timeline cell width is decreased when the cell size falls behind the specified range and the timeline view mode is changed based on the current zooming levels.

Zoom to fit

This support is used to view all the tasks available in a project to specific timespan which is compatible with available area on the chart part of Gantt Chart. When users click the ZoomToFit icon, then all the tasks are rendered within the available chart container width.

Copied to clipboard
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Toolbar="@(new List<string>() { "ZoomIn", "ZoomOut", "ZoomToFit" })" Height="450px" Width="700px">
<GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" Child="SubTasks" Dependency="Predecessor">
</GanttTaskFields>
<GanttLabelSettings LeftLabel="TaskName" TValue="TaskData"></GanttLabelSettings>
</SfGantt>

@code{
public List<TaskData> TaskCollection { get; set; }
protected override void OnInitialized()
{
    this.TaskCollection = GetTaskCollection();
}

public class TaskData
{
    public int TaskId { get; set; }
    public string TaskName { get; set; }
    public DateTime StartDate { get; set; }
    public DateTime EndDate { get; set; }
    public string Duration { get; set; }
    public int Progress { get; set; }
    public string Predecessor { get; set; }
    public List<TaskData> SubTasks { get; set; }
}

public static List <TaskData> GetTaskCollection() {
List <TaskData> Tasks = new List <TaskData> () {
    new TaskData() {
        TaskId = 1,
        TaskName = "Project initiation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 2,
                TaskName = "Identify Site location",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "0",
                Progress = 30,
            },
            new TaskData() {
                TaskId = 3,
                TaskName = "Perform soil test",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "4",
                Progress = 40,
                Predecessor = "2"
            },
            new TaskData() {
                TaskId = 4,
                TaskName = "Soil test approval",
                StartDate = new DateTime(2019, 04, 02),
                Duration = "0",
                Progress = 30,
                Predecessor = "3"
            },
        })
    },
    new TaskData() {
        TaskId = 5,
        TaskName = "Project estimation",
        StartDate = new DateTime(2019, 04, 02),
        EndDate = new DateTime(2019, 04, 21),
        SubTasks = (new List <TaskData> () {
            new TaskData() {
                TaskId = 6,
                TaskName = "Develop floor plan for estimation",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "3",
                Progress = 30,
                Predecessor = "4"
            },
            new TaskData() {
                TaskId = 7,
                TaskName = "List materials",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "3",
                Progress = 40,
                Predecessor = "6"
            },
            new TaskData() {
                TaskId = 8,
                TaskName = "Estimation approval",
                StartDate = new DateTime(2019, 04, 04),
                Duration = "0",
                Progress = 30,
                Predecessor = "7"
            },
        })
    }
};

return Tasks;
}
}

Alt text

Zoom action by methods

Zooming action also can be performed on external actions such as button click using the ZoomIn(), ZoomOut(), and FitToProject() built-in methods.

Alt text