Selection in Blazor Gantt Chart Component

23 Jun 202616 minutes to read

The Selection feature provides the ability to highlight a row or cell in the Gantt component. Selection can be performed using arrow keys or mouse clicks.

By default, selection is enabled. To disable selection, set the AllowSelection property to false.

The Gantt component supports two types of selection that can be set by using the SelectionSettings.Type property. They are:

  • Single: Allows selection of only one row or cell at a time. This is the default behavior.
  • Multiple: Enables selection of multiple rows or cells. To perform multi-selection, press and hold the Ctrl key (on Windows/Linux) or Cmd key (on macOS) while clicking the desired rows or cells.

Selection mode

The Blazor Gantt Chart component supports three selection modes, configured using SelectionSettings.Mode property. They are:

  • Row: Selects only rows. This is the default mode.
  • Cell: Selects only individual cells.
  • Both: Enables selection of both rows and cells at the same time.
@using Syncfusion.Blazor.Gantt
@using Syncfusion.Blazor.Grids
@using Syncfusion.Blazor.DropDowns

<div style="margin-bottom:5px">
    <label style="padding: 30px 2px 0 0;font-weight:bold"> Choose selection mode: </label>
    <SfDropDownList TValue="Syncfusion.Blazor.Grids.SelectionMode" TItem="DropDownOrder" @bind-Value="@SelectionModeValue" DataSource="@DropDownData" Width="100px">
        <DropDownListFieldSettings Text="Text" Value="Value"></DropDownListFieldSettings>
        <DropDownListEvents ValueChange="@OnChange" TValue="Syncfusion.Blazor.Grids.SelectionMode" TItem="DropDownOrder"></DropDownListEvents>
    </SfDropDownList>
</div>

<SfGantt DataSource="@TaskCollection" Height="450px" Width="700px">
    <GanttTaskFields Id="TaskID" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" ParentID="ParentID"></GanttTaskFields>
    <GanttSelectionSettings Mode="@SelectionModeValue"></GanttSelectionSettings>
</SfGantt>

@code {
    private List<TaskData> TaskCollection { get; set; }
    public Syncfusion.Blazor.Grids.SelectionMode SelectionModeValue { get; set; } = Syncfusion.Blazor.Grids.SelectionMode.Both;
    public class DropDownOrder
    {
        public string Text { get; set; }
        public Syncfusion.Blazor.Grids.SelectionMode Value { get; set; }
    }
    List<DropDownOrder> DropDownData = new List<DropDownOrder>
    {
        new DropDownOrder() { Text = "Both", Value = Syncfusion.Blazor.Grids.SelectionMode.Both },
        new DropDownOrder() { Text = "Row", Value = Syncfusion.Blazor.Grids.SelectionMode.Row },
        new DropDownOrder() { Text = "Cell", Value = Syncfusion.Blazor.Grids.SelectionMode.Cell },
    };

    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public void OnChange(ChangeEventArgs<Syncfusion.Blazor.Grids.SelectionMode, DropDownOrder> Args)
    {
        SelectionModeValue = Args.Value;
    }

    public class TaskData
    {
        public int TaskID { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime? EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public int? ParentID { get; set; }
    }

    public static List<TaskData> GetTaskCollection()
    {
        List<TaskData> Tasks = new List<TaskData>()
        {
            new TaskData() { TaskID = 1, TaskName = "Project initiation", StartDate = new DateTime(2022, 04, 05), EndDate = new DateTime(2022, 04, 08) },
            new TaskData() { TaskID = 2, TaskName = "Identify Site location", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentID = 1 },
            new TaskData() { TaskID = 3, TaskName = "Perform soil test", StartDate = new DateTime(2022, 04, 05), Duration = "4", Progress = 40, ParentID = 1 },
            new TaskData() { TaskID = 4, TaskName = "Soil test approval", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentID = 1 },
            new TaskData() { TaskID = 5, TaskName = "Project estimation", StartDate = new DateTime(2022, 04, 06), EndDate = new DateTime(2022, 04, 08) },
            new TaskData() { TaskID = 6, TaskName = "Develop floor plan for estimation", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 30, ParentID = 5 },
            new TaskData() { TaskID = 7, TaskName = "List materials", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 40, ParentID = 5 },
            new TaskData() { TaskID = 8, TaskName = "Estimation approval", StartDate = new DateTime(2022, 04, 07), Duration = "0", Progress = 30, ParentID = 5 }
        };
        return Tasks;
    }
}

Toggle selection

Toggle selection allows you to select and deselect a specific row or cell with repeated clicks. To enable this feature, set the EnableToggle property of SelectionSettings to true.

When enabled, clicking a selected row or cell will deselect it, and clicking it again will reselect it—vice versa. By default, the EnableToggle property is set to false.

@using Syncfusion.Blazor.Gantt
@using Syncfusion.Blazor.Grids
@using Syncfusion.Blazor.Buttons

<div style="padding-bottom:20px">
  <SfButton @onclick="ToggleSelection">@buttonText</SfButton>
</div>
<SfGantt @ref="Gantt" DataSource="@TaskCollection" Height="450px" Width="700px">
    <GanttTaskFields Id="TaskID" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" ParentID="ParentID">
    </GanttTaskFields>
    <GanttSelectionSettings Mode="Syncfusion.Blazor.Grids.SelectionMode.Row" Type="Syncfusion.Blazor.Grids.SelectionType.Multiple" EnableToggle="@toggle"></GanttSelectionSettings>
</SfGantt>

@code{
    public SfGantt<TaskData> Gantt;
    private bool toggle = true;
    private string buttonText = "Disable Toggle";

    private void ToggleSelection()
    {
        toggle = !toggle;
        buttonText = toggle ? "Disable Toggle" : "Enable Toggle";
    }

    private List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskID { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime? EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public int? ParentID { get; set; }
    }

    public static List<TaskData> GetTaskCollection()
    {
        List<TaskData> Tasks = new List<TaskData>() 
        {
            new TaskData() { TaskID = 1, TaskName = "Project initiation", StartDate = new DateTime(2022, 04, 05), EndDate = new DateTime(2022, 04, 08), },
            new TaskData() { TaskID = 2, TaskName = "Identify Site location", StartDate = new DateTime(2022, 04, 05), Duration = "3", Progress = 30, ParentID = 1 },
            new TaskData() { TaskID = 3, TaskName = "Perform soil test", StartDate = new DateTime(2022, 04, 05), Duration = "4", Progress = 40, ParentID = 1 },
            new TaskData() { TaskID = 4, TaskName = "Soil test approval", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentID = 1 },
            new TaskData() { TaskID = 5, TaskName = "Project estimation", StartDate = new DateTime(2022, 04, 06), EndDate = new DateTime(2022, 04, 08), },
            new TaskData() { TaskID = 6, TaskName = "Develop floor plan for estimation", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 30, ParentID = 5 },
            new TaskData() { TaskID = 7, TaskName = "List materials", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 40, ParentID = 5 },
            new TaskData() { TaskID = 8, TaskName = "Estimation approval", StartDate = new DateTime(2022, 04, 06), Duration = "0", Progress = 30, ParentID = 5 }
        };
        return Tasks;
    }
}

Drag selection

The Gantt Chart component allows to select range of cells or rows by mouse or touch dragging. To enable this, set GanttSelectionSettings.AllowDragSelection to true and GanttSelectionSettings to Multiple.

  • Drag selection is supported in all selection modes, configurable using the Mode property.
  • When cell selection is enabled, it works with both Flow and Box types defined by CellSelectionMode property.
@using Syncfusion.Blazor.Gantt
@using Syncfusion.Blazor.Grids

<SfGantt DataSource="@TaskCollection" Height="450px" Width="700px">
    <GanttTaskFields Id="TaskID" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" ParentID="ParentID">
    </GanttTaskFields>
    <GanttSelectionSettings  Mode="Syncfusion.Blazor.Grids.SelectionMode.Row" Type="Syncfusion.Blazor.Grids.SelectionType.Multiple" AllowDragSelection="true"></GanttSelectionSettings>
</SfGantt>

@code{
    private List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskID { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime? EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public int? ParentID { get; set; }
    }

    public static List<TaskData> GetTaskCollection()
    {
        List<TaskData> Tasks = new List<TaskData>() 
        {
            new TaskData() { TaskID = 1, TaskName = "Project initiation", StartDate = new DateTime(2022, 04, 05), EndDate = new DateTime(2022, 04, 08), },
            new TaskData() { TaskID = 2, TaskName = "Identify Site location", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentID = 1 },
            new TaskData() { TaskID = 3, TaskName = "Perform soil test", StartDate = new DateTime(2022, 04, 05), Duration = "4", Progress = 40, ParentID = 1 },
            new TaskData() { TaskID = 4, TaskName = "Soil test approval", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentID = 1 },
            new TaskData() { TaskID = 5, TaskName = "Project estimation", StartDate = new DateTime(2022, 04, 06), EndDate = new DateTime(2022, 04, 08), },
            new TaskData() { TaskID = 6, TaskName = "Develop floor plan for estimation", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 30, ParentID = 5 },
            new TaskData() { TaskID = 7, TaskName = "List materials", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 40, ParentID = 5 },
            new TaskData() { TaskID = 8, TaskName = "Estimation approval", StartDate = new DateTime(2022, 04, 06), Duration = "0", Progress = 30, ParentID = 5 }
        };
        return Tasks;
    }
}

Clear selection

To clear selected rows and cells in the Gantt component, use the ClearSelectionAsync method.

@using Syncfusion.Blazor.Gantt
@using Syncfusion.Blazor.Grids
@using Syncfusion.Blazor.Buttons


<div style="margin-bottom: 16px;">
    <SfButton @onclick="select" style="margin-right: 12px;">Select Rows</SfButton>
    <SfButton @onclick="clear">Clear Selection</SfButton>
</div>
<SfGantt @ref="GanttInstance" DataSource="@TaskCollection" Height="450px" Width="700px">
    <GanttTaskFields Id="TaskID" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" ParentID="ParentID">
    </GanttTaskFields>
    <GanttSelectionSettings Mode="Syncfusion.Blazor.Grids.SelectionMode.Row" Type="Syncfusion.Blazor.Grids.SelectionType.Multiple"></GanttSelectionSettings>
</SfGantt>

@code{
    public SfGantt<TaskData> GanttInstance;
    private List<TaskData> TaskCollection { get; set; }

    public void select()
    {
        this.GanttInstance.SelectRowsAsync(new int[] {1,2,3});
    }
    public void clear() {
        this.GanttInstance.ClearSelectionAsync();
    }
   
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }
    
    public class TaskData
    {
        public int TaskID { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime? EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
         public int? ParentID { get; set; }
    }

    public static List<TaskData> GetTaskCollection()
    {
        List<TaskData> Tasks = new List<TaskData>() 
        {
            new TaskData() { TaskID = 1, TaskName = "Project initiation", StartDate = new DateTime(2022, 04, 05), EndDate = new DateTime(2022, 04, 08), },
            new TaskData() { TaskID = 2, TaskName = "Identify Site location", StartDate = new DateTime(2022, 04, 05), Duration = "3", Progress = 30, ParentID = 1 },
            new TaskData() { TaskID = 3, TaskName = "Perform soil test", StartDate = new DateTime(2022, 04, 05), Duration = "4", Progress = 40, ParentID = 1 },
            new TaskData() { TaskID = 4, TaskName = "Soil test approval", StartDate = new DateTime(2022, 04, 05), Duration = "0", Progress = 30, ParentID = 1 },
            new TaskData() { TaskID = 5, TaskName = "Project estimation", StartDate = new DateTime(2022, 04, 06), EndDate = new DateTime(2022, 04, 08), },
            new TaskData() { TaskID = 6, TaskName = "Develop floor plan for estimation", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 30, ParentID = 5 },
            new TaskData() { TaskID = 7, TaskName = "List materials", StartDate = new DateTime(2022, 04, 06), Duration = "3", Progress = 40, ParentID = 5 },
            new TaskData() { TaskID = 8, TaskName = "Estimation approval", StartDate = new DateTime(2022, 04, 06), Duration = "0", Progress = 30, ParentID = 5 }
        };
        return Tasks;
    }
}

Touch interaction

The Blazor Gantt Chart component supports touch interaction, allowing you to intuitively navigate and interact with chart elements on touch-enabled devices like smart phones and tablets. This feature enhances usability by allowing intuitive gestures for selecting and managing tasks.

Single Row selection: Tapping a row on a touch screen automatically selects it, offering a straightforward way to interact with the chart.

Multiple Row selection: To select multiple rows, tap a row to display a popup that activates multi-selection mode. After tapping the popup, continue tapping the desired rows to select them. This allows you to select multiple rows simultaneously, as illustrated below:

Multiple selection in Blazor Gantt Chart